Bakeware and baking equipment manufacturer, Taichung

Problem
size behind the meter storage and review the time of use economics for a bakeware and baking equipment manufacturer.

Work
  • analysed the time of use bill, tested storage configurations against the plant's production schedule, and reviewed the resulting economics.

batch production, not a flat load

demand followed the plant's batch production schedule rather than a flat industrial load, which shifted the best charge and discharge windows away from the tariff's default assumption.

Consequence
the dispatch schedule was built around the production calendar rather than the tariff's standard peak and off peak windows.